TITLE:
ORDER PROCESSING & PRODUCTION PLANNING
SCOPE
4.1.0 The
following procedure details the method used by the company to ensure that
production is planned effectively and efficiently.
PROCEDURE
Order Processing
4.1.1 The
company issues a works order which is a five part order set and is known
historically as the 'A' sheets.
4.1.2 Three
copies of the 'A' Sheets (white, pink and yellow) are received from the
Administration Department by the Production Controller for all orders to be
processed.
4.1.3 Each
order is recorded by the Production Controller onto the 'A' sheet register
which is used to monitor the progress of the order and is updated as
appropriate, as information becomes available.
4.1.4 The
'A' sheet register details the following information:-
a. 'A'
sheet number.
b. Date
'A' sheet issued.
c. Bill
of materials issued.
d. White
copy returned.
e. Invoice
month.
f. P.O.D.
copy return.
g. Notes.
4.1.5 Each
order is then logged onto the computer system in the production planning
database. This information is used to produce management reports, order bank
and manufacturing priorities by due-date spreadsheets, which are used to plan
and control all manufacturing activities through the various departments.
4.1.6 Orders
are categorised into three distinct types which are detailed as follows:-
a. BT/Factored/Spares
products
b. Made
to order products
c.
Contracts (Set-out orders)
4.1.7 In
the case of 'made to order' type products the Production Controller delays
entering the details onto the computer production planning database until he
has to accumulated a weeks orders. These orders are then segregated into
product types with each type being allocated with a unique batch number and
logged onto the computer under this number.
BT/Factored/Spares Orders
4.1.8 For
all BT/factored/Spares orders the Stock Controller shall enter the stock
control system and print off the computer a standard 'bill of materials' for
each product to be supplied.
4.1.9 The
bill of materials are then attached to the 'A' sheets and filed in the stores
department to act as a picking list for the stores personnel. When all parts
are available the 'A' sheets are forwarded to the Production Controller who
will initiate the sub-assembly/assembly of the order.
4.1.10 The
activity of generating the bill of materials also allocates the parts from the
stock records.
Made to Order Products
4.1.11 For
all made to order products ie.
·
CPD Consortium Purchasing Division,
·
CAT Catalogue Batch,
·
Lancashire Benches,
·
Library and,
·
Play Panels
the
'A' sheets are forwarded to the Production Controller who will prepare a 'bill
of materials' utilising the Woodman computer programme or by manual processes.
4.1.12 Upon
completion of the bill of materials the Production Controller shall create an
order file which is used to initiate and control the production activities. The
order file shall contain the following documents:
·
'A' sheets
·
Cutting sheets
·
Identification cards
·
Final inspection tickets
·
Issue sheets
·
Assembly and sub-assembly sheets
Contracts (Set outs)
4.1.13 For
all contract orders the green copy 'A' sheet(s) are forwarded to the contracts
department who will produce a 'bill of materials' utilising the Woodman
computer programme or by a manual process. │
4.1.14 Where
there is a requirement within a contract order for BT/Factored/Spares products
then the relevant Contract Manager shall upon completion of the 'bill of
materials' modify the green copy 'A' sheet(s) to include any BT/Factored/Spares
products and signs and dates the amendment as verified.
4.1.15 A
photocopy of the amended green copy 'A' sheet(s) are then returned to the
Customer Service Manager/Sales Administrator who will update the order intake
computer programme to include the amendments and re-print the 'A' sheets.
Amended 'A' sheets will be identified by a suffix code 'A', the amendment issue
and date and the details of the amendment. The new 'A' sheets are then distributed as per the original
or by a manual process.
4.1.16 Upon
completion of the bill of materials the Contract Manager shall create an order
file which is placed into the factory tray and subsequently forwarded to the
Production Control Department to initiate and control the production
activities. The order file shall contain the following documents:
·
Bill of materials (Control Dockets)
·
Cutting sheets
·
Final inspection tickets
·
Assembly and sub-assembly sheets
·
Assembly and sub-assembly drawings
·
Identification cards
·
Issue sheet
Bill of Materials
4.1.17 The
'bill of materials' is a multi-page document which lists all items to be used
in manufacturing a product. Included are all relevant contract information,
works order/batch number, date, page number and a breakdown of part
descriptions, quantities, stock numbers, drawing numbers, purchase order
numbers, etc.
Order Bank Spreadsheets
4.1.18 Order
bank spreadsheets are printed off the production planning database as necessary
to control the top level production planning of all orders and contains the
following information:-
·
Line number
·
Delivery day
·
Contract responsibility
·
Fix start
·
Product type/Batch number
·
Fix finish
·
Works order number
·
Comments
·
Contract title
·
Value
·
Liquidated damage
·
Month to be manufactured
·
Delivery area/Client date
·
Actual delivery date
·
Target date/Purchase
·
order number
·
Delivery date
·
Status
·
W/C date
4.1.19 The
order bank spreadsheets are then printed as appropriate and distributed to the
following personnel:
·
Operations Director
·
Stock Controller
·
Production Manager
·
Installation Manager
·
Contract Managers
·
BT Supervisor
·
Production Controller
·
Stock Controller
Manufacturing Priorities by Due-date Spreadsheet
4.1.20 The
manufacturing priorities by due-date sheet is a spreadsheet printed off the
production planning database by the Production Manager to control the
production routing of made to order and contract type orders through all
departments.
4.1.21 The
manufacturing priorities by due-date sheet details the following information;
·
Date
·
Issued
·
Works order number/batch number
·
Departments
·
Contract name
·
Order value
·
Due date
·
Production
·
Comments
·
Order date
·
Region
·
Date deliver
Weekly Production Meetings
4.1.22 Each
week, two production meetings are convened to facilitate the effective and
efficient control of all production activities.
4.1.23 These
meetings shall take place on a Monday and Tuesday mornings and shall cover the
following order types:
Monday - Contracts (Set-outs), Made to Order
Products, In-house Purchases
Tuesday - BT Products
4.1.24 In
attendance at the meetings shall be the following personnel as appropriate:
·
Operations Director
·
Production Manager
·
Contract Managers (Monday only)
·
Production Controller
·
Installation Manager (Monday only)
·
BT Supervisor (Tuesday only)
·
Stock Controller (Tuesday only)